Costa del Sol Promise Tracker

Key Takeaways

  • Headlines are common. Reality is more complex. This tracker follows commitments from public promise through feasibility, funding, permitting, construction and operational reality.
  • EU-mandated systems tend to land more cleanly. EES, the national short-term rental registry and the golden visa abolition all reached implementation, even after delays in some cases.
  • Transport promises need the most caution. Rail and airport commitments often move through study, tender and partial-operation phases before residents feel a practical improvement.
  • Opening does not always mean normal. A ribbon-cutting, partial reopening or regulatory launch can still leave capacity, service, loophole or compliance problems for residents.
  • This page is updated monthly. The current check uses WaypointSur beat-round verification through 28 August 2026, then changes after the next full beat round.

🌊 Get the WaypointSur Briefing

Free weekly intel for expats on the Costa del Sol. Deadlines, workarounds, and admin shortcuts only long-term residents know.

Subscribe Free →

Headlines make Costa del Sol projects, rule changes and development announcements sound simple. This tracker follows what was promised, what has actually happened and which claims are still too early to plan around.

The Costa del Sol Promise Tracker is WaypointSur’s running record of public commitments that matter to residents. It is not a scorecard for one party or one authority. It is a practical way to separate a useful planning signal from a headline that still has to survive funding, permits, works, court challenges and operational follow-through.

Last updated: 28 August 2026. Scope: Costa del Sol infrastructure, regulation and economic-development commitments with direct resident impact.

How the Costa del Sol Promise Tracker Works

The important question is not whether an authority, company or institution said something would happen. The question is whether the delivery mechanism is visible enough that residents should plan around it.

Each entry includes a First dated reference field. This is the earliest dated marker in the current tracker package, such as an announcement, law, tender, construction start, opening window or failure marker. It is not always the first press mention ever published.

Where an entry includes a Source trail, the links are there to show how the public record developed. Announcement coverage can make a project sound closer than it is; current-reality links show the later milestone, delay, legal text, official page or failure marker that residents should use for planning.

Court challenge tracking is being expanded. Some promises do not fail because the announcement was false. They become harder to rely on because courts change the legal path after launch. The Madrid ZBE ruling is the first active test case being folded into the tracker so future updates can show court-challenge trajectories more clearly.

  • ✅ Delivered arrived as promised, or late but now operational.
  • 🔵 In progress funding, works, tendering or formal implementation is active.
  • 🟡 Stalled a promise exists, but visible progress or public confirmation has slipped.
  • 🔴 Missed a stated date passed without delivery.
  • ⚪ Announced commitment made, but no strong delivery mechanism yet.
  • ❌ Cancelled the original project or promise has been abandoned or reset.

Spanish terms used below: autonomo means self-employed worker, VUT means vivienda de uso turistico or tourist-use dwelling, ZBE means zona de bajas emisiones or low-emission zone, and TIE means tarjeta de identidad de extranjero or foreigner identity card.

The Pattern Behind the Tracker

The strongest pattern is that commitments backed by EU rules, legally durable legislation or signed construction contracts behave differently from commitments that are still political, promotional, study-led or vulnerable to court challenge. Residents should treat a feasibility study, design tender or mayoral endorsement as an early signal, not as a delivery date.

Four operating lessons show up repeatedly. First, EU-mandated systems such as EES, the national short-term rental registry and healthcare-access standardisation tend to arrive more reliably than locally volunteered projects. Second, December and August are common moments for quiet delay, because public attention is weaker. Third, an opening ceremony can precede normal service by months. Fourth, a feasibility study often means the next study has started, not that construction is close.

Use this page alongside deeper WaypointSur guides on public transport in Malaga and the Costa del Sol, Malaga airport transfers, short-term rental regulations by housing type, VeriFactu Spain and business networking on the Costa del Sol.

Infrastructure Commitments

Infrastructure commitments are the hardest to read because the visible promise is often several steps away from resident benefit. A line can be tendered, partially reopened or ceremonially launched while capacity, frequency or journey reliability remains below what residents were told to expect.

Rail

AVE Madrid–Málaga: Álora Landslide Restoration

✅ Delivered — after six missed targets

What was promised
Full double-track restoration after Feb 4 2026 landslide blocked the Álora section
By whom
ADIF / Ministry of Transport
First dated reference
4 February 2026, when the Álora landslide created the restoration commitment.
Promised timing
Multiple targets set — Feb 2, Feb 8, Feb 16, Mar 23 all missed; partial single-track April 30 2026; full double-track end 2026
Reality
Delivered. The second track through Álora reopened on 17 July 2026, fully restoring the Madrid–Málaga line, and Renfe added 8 weekly trains from the same date. The delivery came 12 days after Adif had publicly declined to give any date (5 July), and roughly five months ahead of the last end-2026 framing — after six earlier targets (Feb 2, Feb 8, Feb 16, Mar 23, June, end-2026) had come and gone. Single track had been the operating mode since the partial restoration of April 30 2026, running ~20 minutes slower. Pre-crisis capacity and journey times return from 17 July.
Last checked
2026-07-17

Cercanías C2 Álora Section

🔵 In progress — running, disruption-prone

What was promised
Restoration of C2 service disrupted by the same Feb 4 2026 landslide
By whom
ADIF / Renfe
First dated reference
4 February 2026, when the same landslide disrupted the C2 section.
Promised timing
No date given
Reality
The C2 Málaga–Álora service is running again, but fragile: Adif improvement works forced a partial suspension between Cártama and Álora from 22 May to 8 June 2026, and a signalling fault at Aljaima on 15 June caused another temporary halt, since repaired. Guadalhorce valley commuters should expect further short-notice disruption while the Álora corridor works continue through the summer.
Last checked
2026-07-03

Tren Litoral (Nerja–Algeciras coastal rail)

🔵 In progress (study phase)

What was promised
€992K feasibility study for 195km coastal rail connecting Nerja, Málaga, Marbella, Estepona, and Algeciras
By whom
Ministry of Transport
First dated reference
May 2025, when the current feasibility study was contracted.
Promised timing
Study results were promised for late 2026; delivery has now been extended to April 2027. Construction realistically 2040s
Reality
This is at least the fifth feasibility study in 25 years. The current €992K study was contracted May 2025. In August 2026 the ministry granted a four-month extension, moving the study’s delivery from November 2026 to 2 April 2027, with a five-section Nerja–Algeciras structure confirmed. Full project cost: €6.7 billion. Construction start: 2040s at earliest. Cataluña’s Rodalies network received €8 billion in committed capital over the same period.
Last checked
2026-08-28

Cercanías C1 2027 Track Upgrade

⚪ Announced

What was promised
5.5-month closure of the Málaga–Fuengirola line for track doubling and station improvements
By whom
ADIF / Ministry of Transport
First dated reference
September 2025, when the 2027 C1 closure and upgrade were announced.
Promised timing
Closure Q4 2027 – Q1 2028; reopening with 60% capacity increase and 15-min frequency
Reality
Announced September 2025. Works not yet started. March 2026 reporting suggests partial doubling may not deliver increased train frequency as promised.
Last checked
2026-05-22

Aviation

Málaga Airport DORA III Expansion

⚪ Announced

What was promised
€1.5B terminal expansion doubling size (80,000→140,000m²); 36M passenger capacity by 2031
By whom
AENA
First dated reference
September 2025, when the design tender closed in the current DORA III expansion trail.
Promised timing
DORA III regulatory approval September 2026; construction 2027; completion 2031
Reality
Design tender closed September 2025. DORA III regulatory framework not yet approved. First four months of 2026 already hit a record 7.7M passengers — the existing terminal is being overtaken by demand before construction has started.
Last checked
2026-05-22

eVTOL Air Taxi Málaga–Marbella

🔵 In progress — new EU-funded project

What was promised
15-minute electric air taxi service between Málaga airport and Marbella; commercial service from 2030; demo flights H2 2025 (original AENA/Lilium framing)
By whom
AENA / Enaire (Verti-Go consortium, successor to the Lilium-era OperA project)
First dated reference
Before October 2024, when Lilium’s insolvency became the first clear failure marker in the original source trail.
Promised timing
Demo flights H2 2025 (missed, Lilium-era); commercial 2030 (original); Verti-Go now targets Málaga–Marbella demonstration flights in 2028
Reality
Lilium filed for insolvency October 2024 and the original demo flights did not happen. The route has since resurfaced under a different vehicle: Verti-Go, an EU-funded advanced air mobility integration project (June 2026–May 2029, €6.77M budget, ~€5M EU funding) with a 12-partner consortium including Aena, Enaire, Eurocontrol, CRIDA, Vertical Aerospace and lead partner Honeywell Aerospace, announced July 2026. It targets Málaga–Marbella eVTOL demonstration flights in 2028 (projected ~15 minutes versus ~40 minutes by road). This is a funded, named successor project, not the same effort as the failed Lilium partnership — residents should treat 2028 as a demonstration-flight target, not a confirmed commercial service date.
Last checked
2026-09-04

Construction & Utilities

Málaga Metro Line 2 — Hospital Civil Extension

🔵 In progress

What was promised
1.8km underground extension with 3 new stations; EIB €150M loan
By whom
Junta de Andalucía
First dated reference
May 2024, when construction began.
Promised timing
Opening ~2027
Reality
Under construction since May 2024; EIB loan signed March 2025. All three sections are in execution, but the 2027 date no longer adds up. The final 510m section (Eugenio Gross–Blas de Lezo) was signed in May 2026 for €48.2M on a 36-month clock and began execution in July 2026 with survey and geotechnical work only, heavy machinery still pending in August. Section 1 struck the largest Roman necropolis in Málaga’s history (~700 tombs), forcing a reprogramming ordered by the Consejería de Cultura in December 2025 and a second contract modification in May 2026. Section 2 stands at roughly 17%. No official new opening date has been given; the contract arithmetic points to 2029. A metro stop at the new Hospital Virgen de la Esperanza remains committed.
Last checked
2026-08-21

AP-7 Tunnel Renovation (20 tunnels, Málaga–Guadiaro)

🔵 In progress

What was promised
€42.6M upgrade of 20 tunnels for safety, lighting, fire detection; concurrent with anti-noise works near Marbella
By whom
Ministry of Transport
First dated reference
By May 2026 in the current source trail; the original announcement date is not captured in this tracker package.
Promised timing
Completion mid-2027
Reality
Works underway. Night lane closures and disruption ongoing through June 2026 for the anti-noise phase. On track.
Last checked
2026-05-22

Málaga Port Cruise Terminal Expansion

🔵 In progress

What was promised
New terminal (1,270m²), Heredia Quay refurbishment, onshore power supply; EIB €50M loan
By whom
Port Authority of Málaga
First dated reference
2025, when the EIB loan was signed and the current expansion trail became concrete.
Promised timing
Completion 2027
Reality
EIB loan signed 2025. Construction underway. On track for 2027.
Last checked
2026-05-22

Hospital Virgen de la Esperanza (new Málaga hospital)

🔵 In progress

What was promised
€543M hospital on Hospital Civil grounds; 815 rooms, 48 operating theatres; Andalucía’s largest hospital
By whom
Junta de Andalucía
First dated reference
2 February 2026, when groundbreaking was delivered.
Promised timing
Groundbreaking February 2026 (delivered); completion ~2032
Reality
Groundbreaking delivered February 2 2026. Construction started. 75-month build puts completion around 2032.
Last checked
2026-05-22

Hospital Costa del Sol Marbella — New Wing

✅ Delivered (11 years late)

What was promised
€100M+ expansion, 40,000m² additional space, 16 operating theatres, radiotherapy and nuclear medicine
By whom
Junta de Andalucía
First dated reference
2007, when the expansion was first announced.
Promised timing
Original 2023; delayed to October 2025; finally delivered March 3 2026
Reality
Delivered March 3 2026 — approximately 11 years after original planning. The expansion was first announced in 2007, reactivated in 2021, then delayed again to 2025 before the final March 2026 delivery.
Last checked
2026-05-22

Axarquía Desalination Plant

🔵 In progress

What was promised
25 hm³/year desalination plant (expandable to 50 hm³); €100M; to address Axarquía water stress
By whom
ACUAMED / Central Government
First dated reference
March 2025, when the engineering review contract was awarded.
Promised timing
Engineering review complete late 2026; inauguration not before 2029
Reality
Engineering review contract awarded March 2025 (18-month duration). Full project tender not yet launched. Earliest inauguration: 2029.
Last checked
2026-05-22

Water & Desalination

Drought emergency framework — Andalusian Mediterranean basins

✅ Delivered

What was promised
An end to the exceptional-drought regime and its restrictions once hydrology recovered.
By whom
Junta de Andalucía (Consejería de Agricultura, Pesca, Agua y Desarrollo Rural)
First dated reference
Exceptional-drought scenario in force since 2022–23; peak restrictions from February 2024.
Promised timing
No fixed date; tied to reservoir and indicator thresholds.
Reality
Orden of 10 April 2026 (BOJA nº 77, 23 April) declared the finalización de la situación de sequía across the demarcation, returning the Guadalhorce-Limonero, Viñuela-Axarquía and Costa del Sol Occidental units to normalidad hidrológica and deactivating the extraordinary framework (per-capita caps, irrigation bans, pool and non-essential-use prohibitions). Málaga province stood at 523 hm³ / 84.9% on 10 August 2026 against 330 hm³ / 53.6% the same week in 2025, with a ten-year average of 289 hm³; La Viñuela at 88% against a low of 12.2 hm³ in January 2024. Context worth keeping: this is the best August since 2013, not a record — six of seven provincial reservoirs sit below their August highs. "Normalidad" is a rung on a reversible ladder, not a permanent status; crossing the indicator thresholds again triggers a new order. Separately, four Antequera-area towns (Alameda, Humilladero, Fuente de Piedra, Mollina) restricted irrigation and pool filling by joint bando on 21 May 2026 on aquifer levels, which recharge over years rather than seasons.
Last checked
2026-08-13

Marbella desalination plant — capacity restoration

✅ Delivered

What was promised
Restore the plant to its full 20 hm³/year nominal output.
By whom
Junta de Andalucía (works) on State-owned infrastructure, operated by Acosol
First dated reference
First emergency phase contracted September 2024 (two contracts, ~€7.35M).
Promised timing
During the drought emergency.
Reality
Inaugurated 8 July 2025, restoring nominal capacity of 20 hm³/year, roughly €15M across two phases. Read the detail: the plant was built in the late 1990s to produce exactly that figure and had degraded to about 6 hm³/year, so this is recovery of designed capacity rather than new capacity. Junta puts it at 15–20% of Costa del Sol Occidental demand. Note that the widely-quoted €8M figure covers phase two only.
Last checked
2026-08-13

Bajo Guadalhorce wellfield (Málaga city)

✅ Delivered

What was promised
Rehabilitate six municipal wells plus a 1,000mm conduit to the El Atabal treatment plant, to reduce reservoir dependence.
By whom
Junta de Andalucía (funding and works), operated by Emasa
First dated reference
Works declared finished at the Consejo de Gobierno session of 16 July 2025; investment €15.7M.
Promised timing
In service for the 2026 season.
Reality
Put into service jointly by the Junta and Ayuntamiento de Málaga on 24 March 2026. Málaga city’s reservoir abstraction fell from 58.4 hm³ in 2023 to 39.1 hm³ in 2024, a 33% cut, though Emasa attributes that to the Fahala and Aljaima wells active since June 2023 rather than to these newer sites. Framing correction worth carrying: the Junta presents the new wells as a drought and emergency reserve, not a standing third of daily supply. Combined programme including Aljaima and Fahala exceeds €21.5M.
Last checked
2026-08-13

N-340 Benalmádena–Torremolinos water main (Autovía del Agua, phase 1)

🔵 In progress — behind

What was promised
Roughly 6km of new 800mm ductile-iron main plus ~2.3km of secondary network along the old N-340 corridor.
By whom
Acosol, in co-financing with the Junta de Andalucía; contractor UTE CHM Infraestructuras–Albaida Construcciones
First dated reference
Declared a matter of general interest by the Mancomunidad assembly on 27 June 2025, after repeated bursts.
Promised timing
Eight-month execution term from a December 2025 start, which puts the earliest finish in August 2026.
Reality
Budget is €13,668,764.98. Works began December 2025 in Benalmádena and February 2026 in Torremolinos, reached 20% in March, passed 50% on 1 June, and the project page still read obras en ejecución on 13 August 2026. Documented pre-works failures on this main: July 2024 (calle Medina Azahara) and May 2025 (Hotel Los Patos), the latter followed by an 80m emergency replacement in July 2025. WaypointSur correction: our 2 December 2025 issue gave the cost as €7.6M, named Sánchez Domínguez-Sando as contractor, and stated a March 2026 finish. The budget and contractor were wrong, and the March date was never reachable against an eight-month term.
Last checked
2026-08-13

Axarquía / Vélez-Málaga desalination plant

⚪ Announced — 3 years, still paper

What was promised
A desalination plant of 25 hm³/year, expandable to 50, for the Axarquía.
By whom
Central government (MITECO / Acuamed), with the users’ Mancomunidad and irrigator boards promoting
First dated reference
MITECO and Acuamed work confirmed 11 March 2023; ~€100M committed and general State interest declared May 2023.
Promised timing
Promoter Jorge Martín, 23 February 2026: "en cinco años esto estará listo", i.e. ~2031.
Reality
Still paper. The anteproyecto was drafted by the water users rather than the State and handed to the ministry on 23 February 2026 at €201,582,629 with a 30-month execution period. The only State contract signed to date is Acuamed’s supervision award of 7 March 2025 to TPF Getinsa Euroestudios, €66,300 plus VAT. So roughly €66,000 has actually been spent against a €201.6M headline, three years in. The definitive project and works tender is projected for end-2026 with nothing yet launched. Cost has doubled from ~€100M in 2023, and the financing is a loan repaid by users, not a grant. A separately promoted private plant has also gone nowhere since 2023.
Last checked
2026-08-13

Mijas–Fuengirola desalination plant (Desaladora de la Costa del Sol)

🔴 Missed — 18 years

What was promised
A desalination plant serving the western Costa del Sol.
By whom
Acuamed (central government)
First dated reference
Planned from 2006; environmental impact assessment January 2008.
Promised timing
Works awarded July 2008 for €61.7M.
Reality
The works were awarded, not merely announced, and the plant was never built. In 2026 the question returned to the drawing board: Acosol formalised a 24-month anteproyecto contract with Ayesa on 14 June 2026 (€710,594, €859,819 including tax) for a proposed western Costa plant of undefined capacity, whose scope formally includes a "no desalination" alternative. Eighteen years from signed contract to reconsidering whether to build at all.
Last checked
2026-08-13

ETAP Río Verde expansion (Marbella)

🟡 Stalled — 22 years

What was promised
Double drinking-water treatment capacity to 4.6 m³/s, serving 11 municipalities from Manilva to Torremolinos.
By whom
Junta de Andalucía
First dated reference
Committed 2004.
Promised timing
Awarded 2008; re-tendered with a five-phase execution plan.
Reality
Works were awarded in 2008 and begun, then suspended in 2012 and the contract liquidated in 2016. Re-tendered in December 2024 / January 2025 at €37.1M (around €39M including licensing), sized for a future served population of up to 1.76 million. Still in adjudication during 2026, roughly two decades after first proposal. Not delivered.
Last checked
2026-08-13

Ramal Este trunk main renewal (Marbella to Torremolinos)

⚪ Announced — design stage only

What was promised
Renewal of the ageing eastern trunk main carrying water from Marbella to Mijas, Fuengirola, Benalmádena and Torremolinos.
By whom
Acosol
First dated reference
Tender published 4 August 2026, reported 5 August 2026 by El Español from the technical pliego.
Promised timing
Bids on the design contract close 18 September 2026. Construction has no published date.
Reality
The older of the Ramal Este’s two parallel mains, the Tubería Primera, dates mostly from the early 1970s, runs about 48km and contains over 16km of Rocla pipe plus several kilometres of asbestos cement. Enough of it is out of service that the Ramal Este now runs effectively on a single main, without designed redundancy. Acosol’s own tender documents describe a rupture at peak summer as capable of cutting or severely reducing supply to around 900,000 people across five municipalities. What has actually been tendered is €1,842,258.05 for design drafting and works supervision on phase 1 only (11.8km between the Albarizas and Artola derivations, all inside Marbella, in three lots). Construction itself is neither tendered, costed publicly, nor scheduled. Sits within a wider €14.5M tender package and a €175M EIB-financed investment plan. No rupture occurred on this line in 2025 or 2026; documented bursts are older (August 2022 Arroyo de la Miel, February 2024 El Chaparral, December 2024 Fuengirola).
Last checked
2026-08-13

Regulatory Commitments

Regulatory commitments often deliver more cleanly than concrete-heavy projects, but the resident impact can still be messy. A law may start on time while portals, agencies, platforms, drivers, landlords or town halls take months to settle into a workable version.

Immigration

Regularización Extraordinaria (500,000 workers)

✅ Delivered — window closed June 30

What was promised
Mass regularisation of undocumented workers; 1-year residence and work permit; minor children receive 5-year permits
By whom
Spanish Government
First dated reference
16 April 2026, when the regularisation window opened.
Promised timing
Window April 16 – June 30, 2026
Reality
Window closed 30 June 2026, non-extendable under RD 316/2026 — no second round. Final balance (Moncloa, 2 July): 1,174,978 applications, 79.6% through the arraigo extraordinario track; 609,737 (52%) already in processing; roughly 11,000 favourable resolutions notified; 159,097 new Social Security affiliations by close. Negative silence (no answer within three months) counts as a denial, and extranjería offices in high-volume provinces are warning of processing strain. The story now is the resolution backlog, not the window.
Last checked
2026-07-03

ETIAS (European Travel Authorisation)

⚪ Announced

What was promised
Pre-authorisation system (€20 fee) for non-EU/EEA visitors entering Schengen; multiple prior delays
By whom
European Commission
First dated reference
2022, the first missed launch target in the current tracker history.
Promised timing
Q4 2026 launch; mandatory April 2027
Reality
ETIAS currently has no official launch date at all. Around 20 July 2026 the EU’s official travel site removed the “last quarter of 2026” launch line, after eu-LISA reported that date was no longer feasible; a revised timeline is expected after the eu-LISA management board meets in September 2026, with 2027 the mainstream expectation. On 11 August 2026 the postponement became formal: the EU announced ETIAS is delayed indefinitely, with no replacement date, citing technical and integration problems in the digital border programme. This was at minimum the fourth stated timeline: previous targets in 2022, 2023, and 2024 all missed. Contingent on EES being fully operational, which only happened in April 2026.
Last checked
2026-08-14

Spain Golden Visa Abolition

✅ Delivered on date

What was promised
End of real-estate-based residency programme for non-EU buyers; Organic Law 1/2025
By whom
Spanish Government
First dated reference
3 April 2025, when the abolition took effect under Organic Law 1/2025.
Promised timing
April 3 2025
Reality
Programme closed April 3 2025 as announced. Existing applications before the deadline were protected. One of the cleaner delivery examples in recent memory.
Last checked
2026-05-22

Housing & Short-Term Rentals

Málaga VUT Moratorium (3-year freeze on new licences)

✅ Delivered — active, with exceptions emerging

What was promised
3-year freeze on new tourist rental registrations in 43 Málaga neighbourhoods exceeding 8% saturation
By whom
Málaga Ayuntamiento
First dated reference
14 January 2025, when the freeze took effect.
Promised timing
Effective January 14 2025 through approximately August 2028
Reality
Delivered January 14 2025, though May 2026 reporting showed roughly 100 new tourist apartments approved through the cambio de uso (change of use) loophole, with a Plan Especial under development to close gaps. On 1 July 2026 the city council went further and approved a three-year ban on new tourist apartments, aparthotels, hotels, hostels and guesthouses across all residential zones, effective days after appearing in the official gazette; projects with pre-existing applications are exempt, and the advance notice is expected to trigger a rush of applications before it takes force.
Last checked
2026-07-03

National Short-Term Rental Registry (NRU)

❌ Annulled by court

What was promised
Mandatory Unique STR Registry under Royal Decree 1312/2024; platforms to remove unregistered listings within 48 hours
By whom
Spanish Government
First dated reference
2 January 2025, when the registry opened under Royal Decree 1312/2024.
Promised timing
Registry open January 2 2025; mandatory enforcement July 1 2025
Reality
Annulled. The Tribunal Supremo (sentencia 620/2026, May 2026) struck down the national Registro Único de Arrendamientos, ruling the state lacked competence to create a national registry overlapping the existing regional ones. What survives: the digital single window and the platform data-transmission and statistical obligations. So Costa holiday-let owners still face data duties, but the mandatory national registry number itself is gone.
Last checked
2026-06-19

Non-EU Buyer 100% Property Surcharge

🟡 Stalled

What was promised
100% tax surcharge on property purchases by non-EU buyers; announced by President Sánchez
By whom
Spanish Government / PSOE
First dated reference
January 2025, when President Sánchez publicly proposed the surcharge.
Promised timing
No parliamentary date set
Reality
Still a proposal as of May 2026. Faces constitutional challenges and European Commission proceedings. No parliamentary committee vote scheduled. No implementing legislation drafted.
Last checked
2026-05-22

Marbella PGOM (new urban plan)

🔵 In progress

What was promised
First new General Municipal Ordinance Plan in 40 years; replacement for the 1986 PGOU under the LISTA framework
By whom
Junta de Andalucía / Marbella Town Hall
First dated reference
22 February 2026, when the Junta approval milestone was reached in the current source trail.
Promised timing
Junta approval February 22 2026 (delivered); full ratification 2026-2028
Reality
Junta formally approved February 22 2026 — a major milestone. The extraordinary plenary for provisional approval is confirmed for 29 July 2026, with a press conference on 17 July and the plan documents on public display at the Palacio de Congresos into early September. Definitive Junta approval still follows, and property-level rules wait for the detailed plan (POU) through 2027-2028.
Last checked
2026-07-03

Tax & Business

VeriFactu Digital Invoicing (real-time verification)

🔴 Missed — 12-18 months delayed

What was promised
Real-time digital invoicing system for all businesses and autónomos to combat tax fraud
By whom
AEAT / Government
First dated reference
1 January 2026, the original implementation deadline later missed.
Promised timing
Original January 1 2026; pushed via RDL 15/2025 signed December 23 2025 to January 2027 (companies) and July 2027 (autónomos)
Reality
Missed the January 1 2026 deadline. The deferral Royal Decree was signed on December 23 2025 — three business days before the original implementation date. Companies now face January 2027; autónomos July 2027.
Last checked
2026-05-22

Environment & Traffic

Málaga ZBE Phase 1

✅ Delivered — annulled by TSJA, under appeal

What was promised
437-hectare low-emission zone in Málaga city centre; 97 cameras; non-Málaga vehicles without DGT label banned; €200 fines
By whom
Málaga City Council
First dated reference
30 November 2025, when Phase 1 was delivered and enforcement began.
Promised timing
November 30 2025
Reality
Delivered 30 November 2025 and enforcing. However, a TSJA ruling of 11 June 2026 annulled the ordinance as discriminatory (padrón-based exemptions). The ruling is not firm; the council keeps the zone in force while weighing a casación appeal, and around 35,000 €200 fines could become reclaimable if the annulment stands. Phase 2 (B-label non-residents, November 2026) is now legally doubtful.
Last checked
2026-07-03

Málaga ZBE Phase 2 — B-Label Non-Residents

🟡 At risk — annulled by TSJA; appeal decision expected from September

What was promised
Extension of ZBE restrictions to B-label (yellow sticker) vehicles not registered in Málaga
By whom
Málaga City Council
First dated reference
30 November 2025, when Phase 2 appeared in the same rollout path as Phase 1.
Promised timing
November 2026
Reality
A ruling of the Tribunal Superior de Justicia de Andalucía dated 11 June 2026 annulled Málaga’s ZBE ordinance, finding the padrón/domicile-based exemption system discriminatory under Tribunal Supremo doctrine. The ruling is not yet firm: the city council is keeping the ordinance in force and, according to specialist motoring press reporting in August 2026, has requested a clarification (aclaración) from the court — a procedural step that pauses the deadline for lodging a casación appeal to the Supreme Court. Because August is a non-working month in the Spanish courts, the court’s answer is expected from September 2026; if an appeal is then filed, a final Supreme Court ruling could take six to twelve months. Phase 2 (B-label vehicles not registered in Málaga, stated for 30 November 2026) is built on exactly the exemption logic the court struck down, so treat the November date as legally doubtful. More than 35,000 fines of €200 had been issued through June 2026; they could become reclaimable if the annulment becomes final. Enforcement continues while the appeal question runs — do not treat the zone as void.
Last checked
2026-08-14

V16 Connected Beacon — Mandatory

✅ Delivered — with last-minute chaos

What was promised
V16 emergency beacon (replaces warning triangles) mandatory from January 1 2026; must transmit location to DGT 3.0
By whom
DGT
First dated reference
29 December 2025, when the approved-device list changed three days before the mandate.
Promised timing
January 1 2026
Reality
Delivered January 1 2026. However, the DGT changed the approved beacon list on December 29 2025 — three days before the mandatory date — invalidating beacons that drivers had purchased in good faith. Many drivers were caught with non-compliant devices they had bought weeks earlier.
Last checked
2026-05-22

Border & Travel

EU Entry/Exit System (EES)

✅ Delivered — four missed deadlines across four years

What was promised
Biometric border registration replacing passport stamping for non-EU travelers at Schengen borders
By whom
European Commission
First dated reference
October 2022, the original launch target later missed.
Promised timing
Original October 2022 (missed); November 2023 (missed); October 2024 (missed); April 10 2026 (delivered)
Reality
Launched April 10 2026. Costa del Sol residents holding a TIE are exempt. AGP handling it with 10–20 minute average waits. The four prior deadlines missed over four years created widespread misreporting about a “September 2026 postponement” that never existed — what media reported as a delay was actually a built-in per-airport flexibility mechanism.
Last checked
2026-05-22

Healthcare

Real Decreto 180/2026 — Universal Public Healthcare

✅ Delivered on date

What was promised
Universal healthcare access based on residency regardless of legal status; standardises rules across autonomous communities
By whom
Spanish Government
First dated reference
13 March 2026, when Real Decreto 180/2026 was delivered.
Promised timing
March 13 2026
Reality
Delivered March 13 2026. People without formal residency can apply via responsible declaration. UK S1 certificate holders continue using their existing route.
Last checked
2026-05-22

MiResidencia Digital Residency Portal

🟡 Stalled — possibly quiet rollout

What was promised
Centralised digital portal for residency procedures; €78M budget; 1,200 temporary staff; Q1 2026 rollout
By whom
Ministry of Inclusion
First dated reference
Q1 2026, the promised rollout window.
Promised timing
Q1 2026
Reality
Q1 2026 passed with no public announcement of full launch. Status unclear — may be quietly rolling out in limited form, or delayed. No official confirmation either way.
Last checked
2026-05-22

Economic Development Commitments

Economic-development announcements are useful early signals, but they are easy to overread. Jobs, square metres, hotel flags and strategic-project labels only become resident reality when land, permits, construction contracts and operating dates line up.

Tech & Industry

IMEC Semiconductor Research Centre (Málaga TechPark)

🔵 In progress — on track

What was promised
Belgium’s IMEC building Spain’s first 300mm semiconductor R&D facility; €615M total; 450 jobs; Junta land permission January 2025
By whom
Spanish Government (SETT) / Junta / IMEC
First dated reference
January 2025, when Junta land permission entered the current source trail.
Promised timing
Construction contracts awarded May 2026 (delivered); building permit obtained May 2026; construction start Q1 2027; first equipment H2 2028; operations ~2030
Reality
Progressing as described. Construction contracts (~€168M) awarded May 2026 to Sando+OHLA+Itercon and the building permit obtained the same month. Construction is set to start Q1 2027, first equipment H2 2028, operations around 2030. €615M total (€500M state). One of the few large announcements moving on its stated path. The six-month detailed-design phase began after the May award; post-award technical meetings confirmed July 2026.
Last checked
2026-07-10

Sermatec Lithium Battery Plant (Humilladero, Málaga)

🔴 Missed

What was promised
Europe’s largest LFP lithium battery plant; 10,000m²; 5GWh annual production; 300 jobs; first Sermatec outside China
By whom
Sermatec / Junta de Andalucía
First dated reference
End of 2025, the original operational target that was missed.
Promised timing
Operational “around end of 2025” (original — missed); strategic status valid to December 2027
Reality
Original end-2025 target missed. State incentives were officially confirmed in February 2026 (356 direct jobs), and a new operational target of end-2026 is stated alongside the neighbouring Hygreen plant. But no groundbreaking has been announced and no construction is visible, so this stays a missed-and-watching entry, not an active build. As of 10 July 2026 there is still no construction start; with an 18-24 month build, the stated end-2026 operational target is no longer arithmetically achievable.
Last checked
2026-07-10

Hygreen Energy Electrolyser Factory (Humilladero, Málaga)

🔵 In progress — permitting phase

What was promised
5GW alkaline electrolyser manufacturing plant; €78M; 168 direct jobs
By whom
Hygreen Energy / Junta de Andalucía
First dated reference
May 2025, when strategic-project status was granted.
Promised timing
Strategic status valid to December 2027; operational date unconfirmed
Reality
Strategic status granted May 2025. Permitting fast-tracked. No confirmed operational date and no groundbreaking confirmed. Broader Hygreen plan involves $2.2B in Spanish green hydrogen. As of 10 July 2026 there is still no construction start; the end-2026 operational target stated alongside Sermatec is no longer arithmetically achievable on an 18-24 month build.
Last checked
2026-07-10

Estepona Private University

🔴 Missed — 3 years, nothing built

What was promised
Private university in Estepona; scholarship system for residents; endorsed by mayor
By whom
Estepona Mayor García Urbano
First dated reference
November 2023, when the project was announced.
Promised timing
Operational for 2025-26 academic year (missed)
Reality
Announced November 2023. Nearly three years later: no construction and no Junta authorization — the implantation request sits in trámite with no BOJA decree. The 2025-26 target passed with nothing built, and as of 21 August 2026, weeks before term start and with no legal authorization in existence, a 2026-27 opening is also impossible. Next feasible window: 2027-28.
Last checked
2026-08-21

Málaga TechPark (PTA) Phase 2 Expansion

🔵 In progress

What was promised
Second major expansion adding ~570,000m² developable land; 4 new buildings tendered
By whom
PTA Málaga / Junta
First dated reference
2025, when the current expansion trail appeared in the TechPark performance and planning record.
Promised timing
Partial plan approval 2026 (now achieved); urbanisation works in two phases
Reality
Moving. The Local Government Board approved the revised Partial Plan for the SUS-CA.23 PTA Extension sector (~550,000m²). In May 2026 a €1,257M data centre in the extension was declared a strategic investment for Andalucía (710 construction jobs, 254 in operation). TechPark also recorded a strong 2025: 29,018 workers, €4.896B revenue (+17%). Land-development and purchase steps still lie ahead.
Last checked
2026-06-19

Hospitality

Four Seasons Marbella East (Río Real)

⚪ Announced — 2026 date is not realistic

What was promised
~€700M luxury hotel + branded residences; approximately 2026 hotel opening
By whom
Immobel / Four Seasons
First dated reference
February 2026, when the urbanisation project was presented to Marbella local government.
Promised timing
Hotel “towards end of 2026” (marketing language); residences 2029; full completion 2031-2032
Reality
Advancing in planning, with an ownership flip: Ricardo Arranz, the local promoter who fronted the project for years, sold 90% of the project land to Immobel and Fort Partners in May 2026 and exits. The Junta’s environmental approval (AAU) for the El Pinar I / Río Real site (325,161 m²) cleared in February 2026, with total investment put at €650-740M. Institutional owners with hotel-delivery track records make the project more likely to build — on their timetable. Still pre-construction; realistic build start 2027, full delivery nearer 2031-32. The “2026 opening” line in press materials is marketing framing, not a delivery commitment.
Last checked
2026-07-03

Waldorf Astoria Higuerón Marbella Golf Resort

⚪ Announced

What was promised
€220M ultra-luxury resort; 120 rooms + 120 branded residences; first Waldorf Astoria in Spain
By whom
Higuerón Developments / Hilton
First dated reference
November 2025, when the resort was announced.
Promised timing
Opening 2029
Reality
Announced November 2025. Planning and approval phase. 2029 is the stated opening.
Last checked
2026-05-22

Torre del Puerto — Málaga Port Hotel Skyscraper

❌ Cancelled

What was promised
144m Chipperfield-designed luxury hotel; 382 rooms; ~€200M; Levante Dock
By whom
Al Alfia / Hesperia / Puertos del Estado
First dated reference
Around 2015, based on the source trail’s 10-year process before the December 2025 cancellation.
Promised timing
Completion ~2028 (now cancelled)
Reality
Puertos del Estado scrapped the project in December 2025 and called a new tender. Two court appeals pending. Project reset to square one after approximately 10 years and three design iterations. The port is back to square one.
Last checked
2026-05-22

Puerto Banús — Sale Process

⚪ Announced — no timeline

What was promised
Vidiella family (marina concession holders) exploring entry of financial partner or majority stake sale via EY process
By whom
Vidiella family / EY
First dated reference
April 2026, when the EY sale-process exploration was confirmed.
Promised timing
No timeline stated
Reality
EY process confirmed April 2026. No deal announced. Timeline unknown. Worth watching.
Last checked
2026-05-22

Delivered Hospitality Background

Recent delivered hospitality items are tracked as background rather than full entries: Kimpton Los Monteros in February 2025, Gran Marbella Resort in August 2025, Don Carlos renovation in summer 2025, AluaSoul to Pierre & Vacances in June 2025 and the Marbella desalination tripling in July 2025.

How to Use This Tracker

This tracker is most useful when you are deciding whether a public commitment should change your plan. A delivered or actively contracted commitment can be built into assumptions. A study, proposal, press statement or marketing launch should be treated as a monitoring item until the delivery mechanism becomes concrete.

  1. Check the status, not just the headline. A promised date can be useful, but the current phase matters more.
  2. Look for the delivery mechanism. Funding, legal text, construction contracts, tenders and implementation windows matter more than political language.
  3. Ask who is affected now. A regulatory launch may hit drivers, landlords, autonomos or non-EU travellers before the broader public notices.
  4. Watch partial delivery carefully. Partial reopening, soft launch and pilot phase are not the same as full normal service.
  5. Recheck before relying on a date. The entries here are last checked, but transport, tax and immigration timelines can move quickly.

Related Guides

These WaypointSur guides give practical detail behind several tracker categories. Use them when a commitment has moved from headline risk into something that affects a move, property, business or day-to-day decision.

FAQ

These questions cover how to read the tracker, what it includes and how often it changes. The short version is simple: the page tracks commitments that materially affect Costa del Sol residents, then updates them when the evidence changes.

What does promised vs delivered mean in Spain?

It means separating a public commitment from actual operational delivery. A minister, town hall, airport operator or company may announce a project, but residents should usually wait for funding, legal text, tenders, construction, launch evidence or platform enforcement before relying on it.

Is this tracker only about Costa del Sol projects?

Yes, the scope is Costa del Sol resident impact. Some entries are Spain-wide or EU-wide systems, such as ETIAS, EES, VeriFactu or the national short-term rental registry, but they are included because they directly affect residents, owners, travellers or businesses on the Costa.

How often is this page updated?

WaypointSur updates this page monthly after the full Friday beat round, and sooner when a major status changes. The update line shows the last verification date, and each entry carries its own last-checked date.

Why are feasibility studies marked differently from construction?

A feasibility study is a signal that an idea is being examined, not a commitment that residents can use for planning. Construction, signed contracts and formal legal implementation carry more weight because they show the delivery mechanism has moved beyond assessment.

Does delivered mean there were no problems?

No. Delivered means the commitment reached operational or legal implementation. The notes still record late delivery, reduced capacity, loopholes, last-minute confusion or partial functionality when those details matter to residents.

How can I flag a missing or incorrect commitment?

Email WaypointSur with the announcement, source link and why it matters to Costa del Sol residents. The tracker is limited to commitments with clear resident impact and enough evidence to monitor over time.

Update Log

Last updated: 4 September 2026. 4 September round: one entry updated from the 4 September beat round — eVTOL Air Taxi Málaga–Marbella: moved from stalled (Lilium insolvency, no replacement partner) to in progress, after the EU-funded Verti-Go project (Honeywell Aerospace-led, Aena/Enaire consortium, €6.77M budget) surfaced targeting 2028 Málaga–Marbella eVTOL demonstration flights. No other entry changed status this round. Previous 28 August round: one entry updated from the 28 August beat round — Tren Litoral: the feasibility study’s delivery date moved from November 2026 to 2 April 2027 after a four-month extension granted in August 2026; the study’s five-section Nerja–Algeciras structure was confirmed. No entry changed status. Previous 21 August round: two entries updated from the 21 August beat round — Metro Line 2 reality rewritten (final 510m section signed May 2026 on a 36-month clock, in execution since July 2026 but still at survey stage; a ~700-tomb Roman necropolis forced reprogramming of section 1; the 2027 opening is no longer arithmetically possible, no official re-date yet), and Estepona Private University updated: with no Junta authorization in existence weeks before term start, the 2026-27 academic year is also missed — next feasible window 2027-28. No entry changed status. Previous 14 August round: two entries updated — ETIAS moved from date-scrubbed to formally postponed indefinitely (EU announcement, 11 August 2026; eu-LISA September board still the next decision point), and Málaga ZBE Phase 2: the city requested an aclaración from the TSJA, reported as pausing the appeal deadline, moving the decision window to September 2026 while €200 fines continue. Previous 13 August round: new Water & Desalination section added with eight entries, closing the tracker’s largest gap — the provincial water programme had no coverage here despite being the defining infrastructure story of 2022–2026. Two delivered (Marbella desalination capacity restoration, July 2025; Bajo Guadalhorce wellfield, in service March 2026), one in progress and behind (N-340 Benalmádena–Torremolinos main), one drought framework formally ended (Orden 10 April 2026), and four outstanding: the Axarquía plant (€201.6M announced, ~€66,000 actually spent), the Mijas–Fuengirola plant (works awarded 2008, never built, back to study in 2026), ETAP Río Verde (committed 2004, still in adjudication), and the Ramal Este renewal (design tendered August 2026, construction unscheduled). A WaypointSur self-correction is recorded against the N-340 entry: our 2 December 2025 issue published the wrong budget, the wrong contractor and an unreachable completion date. Previous 29 July round: ETIAS lost its official launch date — the European Commission’s travel site removed the “last quarter of 2026” line around 20 July after eu-LISA reported the date unfeasible, leaving ETIAS date-less for the first time in the tracker’s history; a revised timeline is expected after eu-LISA’s September board meeting. No entry changed status. Previous 17 July round: AVE Álora moved to delivered — the second track reopened 17 July with 8 added weekly Renfe trains, twelve days after Adif had declined to give any date and after six missed targets; no other entry changed status. Previous mid-July check: AVE Álora double track now officially date-less (Adif, 5 July); Sermatec and Hygreen end-2026 operational targets recorded as arithmetically unachievable with still no groundbreaking; IMEC design phase confirmed on its stated path. Previous 3 July refresh: regularisation window closed at 1,174,978 applications (delivered); Málaga ZBE Phases 1-2 marked annulled-by-TSJA-under-appeal; Cercanías C2 moved from stalled to running-but-fragile; Metro Line 2’s 2027 date flagged at risk after a 36-month section award; Marbella PGOM plenary confirmed for 29 July; Málaga’s broader three-year tourist-accommodation ban (1 July) and the Four Seasons ownership flip added. Previous June refresh: national short-term-rental registry moved to annulled after the Tribunal Supremo ruling; PTA Phase 2, IMEC, AVE Álora, Four Seasons and the regularisation deadline updated against current sources. Structure (commitment blocks grouped by category, first dated reference fields, court-challenge tracking) unchanged. Source basis: official announcements, beat-round verification, public records and subscriber intel.

Subscribe to WaypointSur for the weekly Costa del Sol briefing that feeds this tracker.

Andrew Lawrence

About the Author

Andrew Lawrence

A.J. Lawrence is the founder of WaypointSur. After a career spanning development, operations, and growth marketing, he moved to the Costa del Sol in 2022. WaypointSur is the guide he wished existed when he arrived — built from direct experience navigating Spanish bureaucracy, banking, property, and tax as an English-speaking professional.

Add WaypointSur as a preferred source in Google Search:

Waypoint Sur

The Costa Del Sol in your inbox. No fluff.
For the residents who stay — not the tourists who leave.

Subscribe

Get our free weekly newsletter — practical intelligence about life on the Costa del Sol.


© 2026 Waypoint Sur · Newsletter · Guides

Privacy Policy · Terms & Conditions · Cookie Policy